Client:
Statkraft Inc., Norway, (Kargı Kızılırmak Enerji A.Ş.)
Project Location:
Ankara
Working Time:
2011-2013
Installed Capacity:
103.8 MW/167 m3/s
Hydrology Assessment Report for Kargı Dam and HPP Project, which is located on Kızılırmak River with a drainage area of 60 560 km², was prepared. In the scope of this report, inflow series of Kargı Dam were calculated taking into consideration both current and developed conditions of the basin.
Services Offered
- Review of initial (final) design,
- Recommendation on Dam Body Design,
- Programming additional site investigations and evaluation of the works for preparation of foundation improvement measures, and consultancy during the construction stage of the stone columns.
- Consultancy on Tunnel Design,
- Day-to-Day Site Supervision Services (SYDF) on behalf of the Client.