Client:
Betaş Elektrik Taahhüt & Ticaret A.Ş.
Project Location:
Marneuli, Georgia
Working Time:
2015 - 2017
Installed Capacity:
-
Extension of 220/110 kV Substation Marneuli with 500 kV switchgear and Power Transformer Replacement in 220/110 kV Substation Menji.
Services Offered
- Preparation of primary and secondary design drawings in compliance with new materials to be selected for 500/220 kV Marneuli Substation
- One new 220 kV feeder line primary and secondary design for the existing 220 kV Marneuli Substation
- Renovation of power transformer in Menji 220/110 kV Substation