Client:
Çalık Energy Industry and Trade Inc.
Project Location:
Georgia
Working Time:
2014 - 2016
Installed Capacity:
58MWm/160m³/s
The Alpana Project is located on the Rioni River close to Alpana. The Project is consist of a dam with a 50 m height from thalweg, an energy tunnel with 7.3 m diameter and 3025 m length and a hydroelectric power plant with 100MW capacity near Lajanuri and Rioni Rivers junction.
Services Offered
- Water Potential and Energy Generation Calculations
- Preparation of Pre-Feasibility Report and Feasibility Report
- Topographical and Mapping Services
- Design of all Project Components according to Hydraulic and Stability Calculations
- Geological and Geotechnical Investigations and Preparation of related Reports
- Construction Planning and Preparation of Methodology Report
- Preparation of Resettlement Action Plan (Expropriation) Reports
- Preparation of ESIA Reports
- Bill of quantities and overall cost estimate
- Determination of rantability of the Project based on economic analysis.