Kandil Dam & HPP

Kandil Dam & HPP2024-06-06T11:41:50+03:00







Client:
Enerjisa Enerji Üretim A. Ş. (Verbund)
Project Location:
Kahramanmaraş
Working Time:
2007-2014
Installed Capacity:
206.60MWm + 4.88MWm/107.7m3/s



Concrete Faced Rockfill Kandil Dam is 104 m high from foundation and has 350 m crest length. Two diversion tunnels, with 5 m inner diameter and 435 m length, are located at the right bank. The direct intake, which is located again on the right bank, transfers the water to the valve chamber through a 9500 m long power tunnel of 6 m inner diameter. The valve chamber is connected to the powerhouse with 5 m diameter and 233 m long steel penstock. The powerhouse is equipped with two vertical axis Francis turbines. The environmental flow is released to the downstream of the dam via an eco-turbine located between the spillway and dam on the right bank.

Services Offered

Design Phase

  •  Preparation of feasibility design report and drawings,
  •  Preparation of final design reports and drawings,
  •  Preparation of technical specifications,
  •  Programming site investigations and evaluation of the works,
  • Preparation of detailed design drawings for civil works
    Site Supervision during Construction Phase;
  •  Supervision of Construction and Installation,
  • Material Tests, Surveys and Observations,
  •  Quality Control,
  • Hydromechanical Equipment Inspection,
  •  Coordination of Construction Schedule