Hisarcık Tailings Dam, Turkey

Hisarcık Tailings Dam, Turkey2024-06-06T12:06:20+03:00







Client:
Eti Maden İşletmeleri General Directorate
Project Location:
Kütahya
Working Time:
2013 - 2014
Installed Capacity:
-



Hisarcık Tailings Dam is 25m high from the thalweg and 35m from the foundation level. Dam is Designed to provide storage for the boric acid wastes in order not to cause any environmental damages. The dam body is gravity type, Clay Faced and Zoned Random Fill with 983m long crest and total volume of 2,853,800m3. There are two interception channels with 14.68 m3/s discharge capacity. Waterproofing is ensured with combination of geosynthetics such as geomembrane, GCL over the natural clay fill.

Services Offered
  •  Planning Phase,
  •  Final & Detailed Design,
  •  ESIA Report