Kajaki HPP 2nd Unit Assemblage, Afghanistan

Kajaki HPP 2nd Unit Assemblage, Afghanistan2024-06-06T12:13:20+03:00







Client:
Chenab Valley Power Projects Private Ltd.
Project Location:
Kandahar, Afghanistan
Working Time:
2015 - 2016
Installed Capacity:
1x18.5MW/2x16.50m³/s



The Kajaki Dam and HPP is located on the Helmand River 100 miles (161 km) north-west of Kandahar City. The powerhouse is designed with 3 units vertical Francis type turbines each have 16.5 MW capacities. However, only 1st and 3rd units were installed in 1975 and it was commissioned in the same year without placement of the Unit No:2. Rehabilitation of Units 1&3 were completed in 2005 and 2007, respectively.

Services Offered
  •  Design and existing on-site materials control,
  •  Preparation of the 2nd stage reinforced concrete calculations,
  •  Preparation of the Bill of Quantities for concrete, rebars, anchor ties, epoxy and etc.
  •  Preparation of the Methodology
  •  Preparation of As-Built drawings