Nenskra HPP is a high head hydroelectric project with an installed capacity of 210 MW and located on the Nenskra river in the Svaneti region of north-western Georgia.
Main Project Data
Dam Type and Height: Asphalt-Core Rockfill, 130 m
Concrete Lined Headrace Tunnel: 15,100 m
Tunnel between Nankra Weir and Reservoir: 12,400 m.
Installed Capacity: 210 MW
Annual energy generation: 1,194/927GWh

Services Offered
  •  Preparation of Detailed Design based on previously performed Feasibility study and Initial Design.
  •  Phase 1: Execution of Geological and Geotechnical Investigations and Preparation of the Geological & Geotechnical Report

Phase 2: Detailed Design Services;

  • Review of Tender Design
  •  Preparation of Due Diligence Report
  •  Civil works for Nenskra: Headrace Tunnel (TBM tunnels) and Adits incl. Plugs, Surge Shaft, Pressure Shaft, Gate Chamber and Roads.
  •  Civil works for Nakra: Tunnel (TBM Tunnel) and Roads.